NUK York

RES has completed a number of smaller projects at this site, to include a new platform installation, and jacketed pipe work fabrication and installation, the pipework being fabricated in our workshop and transported to, and installed and connected on site.

The system was pressure tested, certificate issued and all completed documentation.

This being a high hygiene site, requiring additional measures to protect the product, all works completed without issue and on time with good feedback on our performance.

All works completed between November 2019 and March 2020 with a value of £75000.

All installation requiring passivating and swab testing due to the nature of the site.

A dedicated site team meant consistency for the client project team, and site knowledge.